Volume 2, Issue 3 |
March 2005 |
![]() |
The garage floor has extremely wet soil conditions
due to the warm weather and this has caused a delay in the project. It is anticipated that the unsuitable soil in the northern part of the garage will be removed and floor preparation will continue. With the pouring of concrete in the northern area it is hoped that the soil conditions will improve in the southern area, therefore we will not have to remove and add any new material. The fire alarm system has been upgraded totally in the Safety Bldg and will be fully tested on Monday, March 14. Have a safe St. Patrick's Day |
![]() |
![]() |
![]() |
![]() |
| Phase II Building Execavation and Garage Construction | |||
|---|---|---|---|
| DePietro Excavation Co |
1. Building Excavation 2. Footer Drains and Backfill 3. Underground Storm Detention System |
10-18-04 01-18-05 01-20-05 |
11-11-04 02-18-05 02-02-05 |
| Abbott Electric | 1. Site Lighting (Rough) 2. Building Wall and Underground Conduit 3. Building Underground Power (New and Existing) 4. Upgrade Fire Detection and Alarm System (Existing |
10-27-05 11-15-04 11-23-05 01-24-05 |
. . . 03-07-05 |
| Northern Valley | 1. Footers and Column Pads 2. Walls and Columns 3. Waterproofing 4. Slab on Brade ( Area A) 5. Beams (Area A) |
11-08-04 11-18-04 01-18-05 03-??-05 02-??-05 |
02-18-05 02-23-05 . . . |
| Doershuk Plumbing | 1. Storm Underground and Catch Basins 2. Sanitary Underground 3. Water Underground Building |
11-30-04 12-28-04 12-16-04 |
. . 12-17-04 |
| W.G. Fairfield | 1. Door Frame Installation | 01-01-05 | |
| GMR Masonry | 1. Masonry Walls | 02-02-05 | 02-23-05 |
| Norment Security | 1. Security Door Frame Installation | 02-02-05 | 02-04-05 |
| Area "A" is the Northern half of the New Receiving and Reception Housing Unit | |||
| Area "B" is the Southern half | |||
![]() |
![]() |