  The garage floor has extremely wet soil conditions due to the warm weather and this has caused a delay in the project.
   It is anticipated that the unsuitable soil in the northern part of the garage will be removed and floor preparation will continue.
   With the pouring of concrete in the northern area it is hoped that the soil conditions will improve in the southern area, therefore we will not have to remove and add any new material.
   The fire alarm system has been upgraded totally in the Safety Bldg and will be fully tested on Monday, March 14.
Have a safe St. Patrick's Day
  Phase II Building Execavation and Garage Construction
DePietro
Excavation Co
1. Building Excavation
2. Footer Drains and Backfill
3. Underground Storm Detention System
10-18-04
01-18-05
01-20-05
11-11-04
02-18-05
02-02-05
Abbott Electric 1. Site Lighting (Rough)
2. Building Wall and Underground Conduit
3. Building Underground Power (New and Existing)
4. Upgrade Fire Detection and Alarm System (Existing
10-27-05
11-15-04
11-23-05
01-24-05
.
.
.
03-07-05
Northern Valley 1. Footers and Column Pads
2. Walls and Columns
3. Waterproofing
4. Slab on Brade ( Area A)
5. Beams (Area A)
11-08-04
11-18-04
01-18-05
03-??-05
02-??-05
02-18-05
02-23-05
.
.
.
Doershuk Plumbing 1. Storm Underground and Catch Basins
2. Sanitary Underground
3. Water Underground Building
11-30-04
12-28-04
12-16-04
.
.
12-17-04
W.G. Fairfield 1. Door Frame Installation 01-01-05  
GMR Masonry 1. Masonry Walls 02-02-05 02-23-05
Norment Security 1. Security Door Frame Installation 02-02-05 02-04-05
 
Area "A" is the Northern half of the New Receiving and Reception Housing Unit