The garage floor drains and the buildings sanitary drain lines are almost all in. Wall pour eight was done on February 8th and it was the last of the wall pours.
Waterproofing of garage walls is about 75% complete and the column to support the corridor bridge was poured on Tuesday, February 22nd.
The architect provided two color boards with the different wall and floor materials to be selected.
A meeting will be held to select the color schemes in the near future.
Here are a few site photos. 

THREE WEEK CONSTRUCTION SCHEDULE:

    FEBRUARY
Company Work Description 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13
Job Meeting 9:00 am   X                           X          
                                             
Abbott Fire Alarm - Existing Bldg   X X X X     X X X X X     X X X X X    
  Underground Service X X X X X     X X X X X                  
  Site Lighting     ?             ?             ?        
                                             
DePietro Excavating Building Subgrade - North   ? X X X     X X                        
  Gravel Base - North         ?     X X X                      
                                             
Northern Valley Prep North - Conc Floor       ? X     X X X X X                  
  Concrete Floor Pour                   ? ? ?                  
  Forming North Half Beams                             ? X X X X    
  Place Rebar - North Beams                                     X    
  Pour Retaining Wall - entrance X                                        
  Form & Pour Bridge Column   X                                      
                                             
Doerschuk Plumbing Set Catch Basin - North X X X                                    
  Set Catch Basin - South       ? X     X X X X X                  
                                             
GMR Masonry Masonry Walls _ North X                                        
  Masonry Walls - South X X                                      
                                             
WG Fairfield Set Frames - South     X                                    
                                             
Architect Penetration Review   X X X X                                
  Security System Design