Volume 2, Issue XI

November 2005

Opps! Repairing an electrical line accidentally cut while trenching for curbing and sidewalk November 17th - emergency generator installed
masons completing the reverse side of the connecting corridors west end masons completing the reverse side of the connecting corridors east end
brickwork continues on the southern end security grate at main air intake
finish grinding work on receiving cells curbing done to vehicle sally port
front entrance walk and some curbing completed November 21st - precast being placed on the southern sections second floor