Volume 1, Issue 2 |
November 2004 |
| We need to name our housing units in the new addition. Presently we
have the following areas in the old jail and need to have something that will not get
confused or confusing when it is called over the radio or paging system. A-Block has:
A-1-A, A-1-B; A-1-C, A-1-D, A-1-DAY, A-2-A, A-2-B; A-2-C, A-2-D, A-2-DAY, How does RH-1, 2, 3, 4, 5, 6, 7, sound? (RH standing for Reception Housing |
|
![]() |
![]() |
Two individuals you might see at the work site are Tom Serra - Project Manager and Jim Rohner - Construction Site Manager. They work for Hammond Construction and their responsibilities are to ensure the site is safe and construction is kept on track and on time,
Jim works out of the construction trailer and Tom coordinates the construction meetings and is the liaison between Hammond Construction and the Commissioners Office.
THREE WEEK CONSTRUCTION SCHEDULE:
| DECEMBER | ||||||||||||||||||||||
| Company | Work Description | 29 | 30 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 |
| Job Meeting | 9:00 am | X | X | |||||||||||||||||||
| Contractors | Shop Submittals | |||||||||||||||||||||
| Beam Penetrations | X | |||||||||||||||||||||
| Abbott | install manhole #2 | X | ||||||||||||||||||||
| rough-in conduit -conc walls | X | X | X | X | X | X | X | X | X | X | ||||||||||||
| DePietro Excavating | InStall Storm Detention System | |||||||||||||||||||||
| Northern Valley | Wall forming -area B | X | X | X | X | X | X | X | X | X | X | X | X | X | X | X | ||||||
| Wall rebar -area B | X | X | X | X | X | X | X | X | X | X | X | X | X | X | X | |||||||
| Wall pour #1 SE -area B | X | |||||||||||||||||||||
| Column forming -area B | X | X | X | X | X | X | X | X | ||||||||||||||
| Column pour -area B | ? | ? | ||||||||||||||||||||
| Wall pour #2 NE -area B | ? | |||||||||||||||||||||
| Column forming -area A | X | X | X | X | X | X | X | |||||||||||||||
| Column pour -area A | ? | |||||||||||||||||||||
| Strip wall forms -pour #1 | X | X | X | X | ||||||||||||||||||
| Doerschuk Plumbing | underground piping -area A | X | X | X | X | X | X | X | X | X | ||||||||||||
| underground piping -area B | ||||||||||||||||||||||
| Norment | resolve questions / submittals | X | ||||||||||||||||||||
| WG Fairfield | door frames -garage | ? | ? | |||||||||||||||||||
| wall embeds | X | X | X | |||||||||||||||||||
| Wachtel / McAnally | beam penetrations review | X | X | X | X | X | X | X | X | X | ||||||||||||
| contractors | 25% work crew -deer hunt | X | X | X | ||||||||||||||||||
| 50% work crew -deer hunt | X | X | ||||||||||||||||||||
| 100% work crew | X | X | X | X | X | X | X | X | X | X | ||||||||||||