Volume 1, Issue 2

November 2004

We need to name our housing units in the new addition.  Presently we have the following areas in the old jail and need to have something that will not get confused or confusing when it is called over the radio or paging system.

A-Block has: A-1-A, A-1-B; A-1-C, A-1-D, A-1-DAY, A-2-A, A-2-B; A-2-C, A-2-D, A-2-DAY,
B-Block has: B-1-N, B-1-S, B-2-A, B-2-B, B-2-C, B-2-D
C-Block has: C-1-N, C-1-S, C-1-DAY, C-2-N, C-2-S, C-2 DAY
D- Section has: D-Front, D-Rear
Minimum Security has: MS-1, MS-2, MS-3
Women's Section has: Catwalk, East Dorm, Mid Dorm, West Dorm

How does RH-1, 2, 3, 4, 5, 6, 7, sound? (RH standing for Reception Housing
If anyone has an idea please advise and we will present it to the Program Development Group (Transition Team

Two individuals you might see at the work site are Tom Serra - Project Manager and Jim Rohner - Construction Site Manager.  They work for Hammond Construction and their responsibilities are to ensure the site is safe and construction is kept on track and on time,

Jim works out of the construction trailer and Tom coordinates the construction meetings and is the liaison between Hammond Construction and the Commissioners Office.

THREE WEEK CONSTRUCTION SCHEDULE:

    DECEMBER
Company Work Description 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Job Meeting 9:00 am   X                           X          
                                             
Contractors Shop Submittals                                          
  Beam Penetrations   X                                      
                                             
Abbott install manhole #2     X                                    
  rough-in conduit -conc walls X X X X X     X X X X X                  
                                             
DePietro Excavating InStall Storm Detention System                                          
                                             
Northern Valley Wall forming -area B X X X X X     X X X X X     X X X X X    
  Wall rebar -area B X X X X X     X X X X X     X X X X X    
  Wall pour #1 SE -area B     X                                    
  Column forming -area B X X X X X     X X X                      
  Column pour -area B     ?             ?                      
  Wall pour #2 NE -area B                                 ?        
  Column forming -area A                     X X     X X X X X    
  Column pour -area A                                 ?        
  Strip wall forms -pour #1                   X X X     X            
                                             
Doerschuk Plumbing underground piping -area A   X X X X     X X X X X                  
  underground piping -area B                                          
                                             
Norment resolve questions / submittals   X                                      
                                             
WG Fairfield door frames -garage                                   ? ?    
  wall embeds                   X X X                  
                                             
Wachtel / McAnally beam penetrations review   X X X X     X X X X X                  
                                             
contractors 25% work crew -deer hunt X X X                                    
  50% work crew -deer hunt       X X                                
  100% work crew               X X X X X     X X X X X